Mumbai Metro, Thane to Kalyan. The unofficial tracker.
All linesEdition of Facts checked Not affiliated with MMRDA
Phase 1, from Kapurbawdi in Thane to Dhamankar Naka in Bhiwandi, is built: on 31 Aug 2026, MMRDA's progress table showed every civil activity complete. Phases 2 and 3 take the line on to Kalyan, with a spur to Ulhasnagar: 19 stations in all, as MMRDA counts them.
VerifiedMMRDA (opens source in a new tab)
Ride the lineEighteen stations, Kapurbawdi to Kalyan, and the Line 5A spur to Ulhasnagar. Scroll to ride the line station by station. Distances follow MMRDA's alignment file of March 2025 to the Ulhas river bridge, and the tentative key plan of March 2026 past it.
Station 1 of 18
0.41 km from the start of the line at Kapurbawdi Reportedopenstreetmap.org (opens source in a new tab)
Change for Metro Line 4 (Wadala-Kasarvadavali)VerifiedMMRDA (opens source in a new tab)
Built as part of Metro Line 4; shared by Lines 4 and 5 Verified
Line 5's first station and its interchange with Line 4. It is built under Line 4's contracts, so MMRDA does not count it among Line 5's stations; the site lists it as Line 5's station 1 (owner's decision, 2026-10-09). Not in the 15-station list on MMRDA's Line 5 page.
Station 2 of 18
2.27 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Planned interchange: Thane Integral Ring Metro (Maha-Metro) Reportedhousing.com (opens source in a new tab)
Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported
Station 3 of 18
5.97 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported
Station 4 of 18
7.86 km from the start of the line at Kapurbawdi ReportedEsri Wayback (opens source in a new tab)
Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported
Station 5 of 18
8.69 km from the start of the line at Kapurbawdi ReportedEsri Wayback (opens source in a new tab)
Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported
Station 6 of 18
10.95 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported
Station 7 of 18
12.58 km from the start of the line at Kapurbawdi ReportedEsri Wayback (opens source in a new tab)
Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported
Station 8 of 18
13.71 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Underground station
Not started Reported
Underground in the revised plan (MMRDA, May 2026); MMRDA's 2025 alignment file still places it on the 2017 route.
Station 9 of 18
16.15 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Not started Reported
Station 10 of 18
17.94 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Not started Reported
Station 11 of 18
18.96 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Not started Reported
Station 12 of 18
21.26 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)
Not started Reported
Not started Reported
New in the revised plan. Its order is MMRDA's list order; whether it lies before or after Kon Gaon on the ground is not published. Other reports call the two stations Kongan West and Kongan East.
Station 14 of 18
23.15 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)
Not started Reported
Called Durgadi Fort in MMRDA's 2025 alignment file, at a different place on the 2017 route.
Station 15 of 18
24.66 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)
Not started Reported
Near Khadakpada Circle, on Khadakpada Road.
Station 16 of 18
25.93 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)
Not started Reported
Station 17 of 18
27.89 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)
Not started Reported
MMRDA's press release calls it Chhatrapati Shivaji Maharaj Path.
Station 18 of 18
29.16 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)
Change for Metro Line 12 (Kalyan-Taloja),Central Railway (Kalyan Junction)VerifiedMMRDA (opens source in a new tab)
Not started Reported
The end of Phase 3. In the key plan it sits 131 m from Line 12's Kalyan station, north of Kalyan railway station; in MMRDA's 2025 file it was 14 m from it.
A hollow line marks track that is not yet open, and a dashed outline the underground stretch. No part of Line 5 has opened.
2.05 km along the spur Reported@Maha7Arindam on X (opens source in a new tab)
Not started Reported
About 500 m from Vithalwadi railway station.
3.43 km along the spur Reported@Maha7Arindam on X (opens source in a new tab)
Not started Reported
MMRDA's press release calls it Chhatrapati Shivaji Maharaj Chowk.
4.68 km along the spur Reported@Maha7Arindam on X (opens source in a new tab)
Not started Reported
The end of the spur. In the key plan it lies about 1.1 km east of Ulhasnagar railway station; MMRDA's press release promises direct access to that station, which the key plan does not show.
The line on a street map. Choose a station to see where it sits, what surrounds it and what the street looks like today. The route to the Ulhas river bridge comes from MMRDA's alignment file of March 2025; Phase 3 and the spur come from the tentative key plan of March 2026.
Route not yet open: MMRDA's alignment file, then the tentative key planVerifiedMMRDA (opens source in a new tab)
Underground stretch, route below ground not published
19.22414, 72.97742 (OpenStreetMap, checked on satellite imagery)
Choose a station on the map or in the list.
The street view for the chosen station appears here.
Station data last reviewed 9 Oct 2026.
The same spots from above, before construction began in January 2020 and in the latest imagery. Drag the handle or use the arrow keys to compare.
The latest image is Esri's newest of this area, captured . The site checks for newer imagery every month; last checked .
A drone flight along Phase 1, from Dhamankar Naka to Kapurbawdi, by InfraUnfiltered, published . Shared with permission. Pick a station to start the video where the flight reaches it.
The video loads from YouTube only when you press play.
The line in figures. Old figures stay on the page, struck through, so you can see how the project changed.
MMRDA's Line 5 page still shows the plan of 2017. The revised plan of 2026 takes the line past Durgadi in a loop to Kalyan, adds a spur to Ulhasnagar and puts Bhiwandi station underground. Here is what changed, figure by figure and station by station.
| Fact | 2017 plan | 2026 plan |
|---|---|---|
| Route | Thane to Kalyan APMC, via Bhiwandi | Thane (Kapurbawdi) to Kalyan, via Bhiwandi and Durgadi, with a spur from Bhoirwadi to Ulhasnagar VerifiedMMRDA (opens source in a new tab) |
| Length | 24.9 km | 34.21 km, with the spur VerifiedMMRDA (opens source in a new tab) |
| Stations | 15 | 19, as MMRDA counts them VerifiedMMRDA (opens source in a new tab) |
| Built | All elevated | Elevated, except Bhiwandi station (underground) Sources conflictMMRDA (opens source in a new tab) |
2017 plan: VerifiedMMRDA (opens source in a new tab)
12 kept, 3 not in the 2026 plan.
9 stations that the 2017 plan did not have.
2026 plan: VerifiedMMRDA (opens source in a new tab)
See both routes on the map: tick "Show the earlier plan's route and dropped stations". The map draws MMRDA's 2025 file of the earlier route.
MMRDA publishes one progress table for Line 5, updated monthly. It does not say which stretch the table covers; its items match Phase 1, the only part being built. It does not publish progress by station.
100%
Every activity in MMRDA's table, 9 of 9:
Every package we could trace, with its value in crore rupees. MMRDA keeps only current notices online, so most of these come from trade press.
| Package | Scope | Floated | Estimate | Awarded | Awarded to | Status | Source |
|---|---|---|---|---|---|---|---|
| CA-28 | Part design and construction of the viaduct and stations from Kapurbawdi to Dhamankar Naka, 12.811 km | Jan 2019 | Not published | Not published7 Jan 2020 | Afcons Infrastructure | Awarded | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-151 | Kasheli depot: stabling yard, sheds, workshops, operation control centre, administrative building and staff quarters | Oct 2022 | ₹472.02 cr | ₹589.56 cr14 Sep 2023 | Rithwik Projects | Awarded | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-159 | Supply of about 6,800 t of head-hardened rails for Lines 5 and 9 | Not found | Not published | None | None | Cancelled | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-166 | Ballastless standard-gauge track from Kapurbawdi to Dhamankar Naka (Phase 1) and the depot line near Kasheli | Not found | Not published | ₹97.4 cr | Paras Railtech | Awarded | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-203 | Supply of about 6,800 t of head-hardened rails for Lines 5 and 9 (second call after CA-159) | Not found | Not published | None | None | Cancelled | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-219 | General consultant for Phase 2, Bhiwandi to Kalyan | Not found | Not published | None | None | Cancelled | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-239 | Overhead electrification, power supply, traction, electrical and mechanical works, lifts and escalators | Feb 2024 | Not published | Not yet | Not yet | Bids opened | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-241 | Rolling stock (22 six-car trains), CBTC signalling and train control, telecom, platform screen doors, and depot machinery at Kasheli | Feb 2024 | ₹2,640.72 cr | ₹2,481 cr31 Oct 2025 | Titagarh Rail Systems | Awarded | VerifiedMMRDA (opens source in a new tab) |
| CA-242 | Automatic fare collection for Phases 1 and 2, with 15 years of maintenance after a 2-year defect period | 20 Mar 2024 | Not published | Not found | Not found | Unknown | Verifiedaiib.org (opens source in a new tab) |
| CA-246 | Architectural finishing and pre-engineered steel at the 6 elevated Phase 1 stations | Not found | Not published | Not published | NACPL-Mansi-UCC JV | Awarded | ReportedThe Metro Rail Guy (opens source in a new tab) |
| CA-256 | General consultant for Phase 2, Dhamankar Naka to Kalyan APMC (13.02 km of viaduct, including 3.5 km underground; the 2023 plan) | 2024 | Not published | Not found | Not found | Unknown | ReportedThe Metro Rail Guy (opens source in a new tab) |
| MMI works | Multi-modal integration facilities at the 6 Phase 1 stations, Balkum Naka to Dhamankar Naka | Jun 2024 | Not published | ₹52.33 cr4 Dec 2024 | K R Construction | Awarded | Verifiedmahatenders.gov.in (opens source in a new tab) |
| MMI consultant | Project management consultant to supervise and monitor the multi-modal integration works at the 6 Phase 1 stations | Aug 2024 | Not published | ₹1.35 cr22 Sep 2025 | Dhruv Consultancy Services | Awarded | Verifiedmahatenders.gov.in (opens source in a new tab) |
| CA-311 | Signage graphics and station furniture (design, supply, installation, testing and commissioning) at the six elevated Phase 1 stations | Apr 2026 | Not published | Not yet | Not yet | Open | Reported@MH04Thane on X (opens source in a new tab) |
| CA-303 | Standard-gauge track work (ballasted and ballastless) at the Kasheli depot | Jun 2026 | ₹84.35 cr | Not found | Not found | Unknown | ReportedFree Press Journal (opens source in a new tab) |
| CA-293 | General consultant for the civil works of Line 5A (Durgadi to Kalyan with a spur to Ulhasnagar), 48 months | Sep 2025 | Not published | None | None | Cancelled | Verifiedmahatenders.gov.in (opens source in a new tab) |
| CA-317 | Phase 2, Dhamankar Naka to Rajnoli Junction (ch. 12,200 to 17,860): design and construction of the viaduct, cut and cover, open ramp and tunnel, with 1 underground and 1 elevated station (excluding architectural finishing and pre-engineered steel) | 29 Oct 2026 | Not published | Not yet | Not yet | Open | Verifiedmahatenders.gov.in (opens source in a new tab) |
| CA-318 | Phase 2 and Phase 3, Rajnoli Junction to Bhoirwadi (ch. 17,860 to 26,140): design and construction of the elevated viaduct, the viaduct integrated with a road flyover, a creek bridge, connecting road ramps and 7 elevated stations (excluding architectural finishing) | 30 Oct 2026 | Not published | Not yet | Not yet | Open | Verifiedmahatenders.gov.in (opens source in a new tab) |
| CA-314 | Line 5A. Part A (ch. 3,596 to 6,521 of Phase 3): elevated viaduct and 1 elevated station. Part B (ch. 383 to 5,272 of the spur): elevated viaduct with an integrated road flyover and 3 double-decker elevated stations | 30 Oct 2026 | Not published | Not yet | Not yet | Open | Verifiedmahatenders.gov.in (opens source in a new tab) |
The trains are ordered. Titagarh Rail Systems is building 22 six-car trains for Phases 1 and 2, with the signalling, platform screen doors and depot machinery, under one contract announced on 31 Oct 2025.

Titagarh Rail SystemsReportedFree Press Journal (opens source in a new tab)
Package CA-241, ₹2,481 crore: 22 trains of 6 cars (132 coaches), built at its plant at Uttarpara, near Kolkata. To be commissioned within 217 weeks. ReportedFree Press Journal (opens source in a new tab)
Maintenance: Five years of comprehensive maintenance in the award reports; the tender set 15 years after a 2-year defect liability period. Sources conflictFree Press Journal (opens source in a new tab)
Traction, from ABB India: Traction and train control (TCMS) for the 22 trains, on 25 kV AC overhead power; automation at grade GoA2, upgradable to GoA4. Reportedmachinist.in (opens source in a new tab)
MMRDA's published figures. MMRDA's Line 5 page lists width, height and length under rolling stock; it does not say whether the length is one car or a whole train, so the page shows it as given. Trains and cars per train come from the contract. VerifiedMMRDA (opens source in a new tab)
All 18 on the line, in order from Kapurbawdi, then the three on the Line 5A spur and the three the 2017 plan had. Names follow MMRDA. Select a station to ride to it, or open its own page.
Station list and order ReportedMMRDA (opens source in a new tab) station count VerifiedMMRDA (opens source in a new tab)
The latest reported milestones, each linked to the article or document, posts on X picked by hand, and news that a script finds every six hours.
Posts by people who follow the project, not by MMRDA. Their claims count as reported.
Better Thane @MH04Thane
MMRDA has floated a tender for signage graphics and station furniture at the six elevated stations of Metro Line 5, Thane-Bhiwandi-Kalyan. Its drawings show the station signs, such as Balkum Naka's, numbered 501, on an orange band.
Found automatically in the outlets' own feeds, not checked by a person. Last new item found .
From the first report in 2017 to the reported opening target. Dates show only as much precision as the source gives.
Every figure on this page links to where it came from. This is how to read the marks next to them.
The full list, with every news and trade source, is in SOURCES.md.
Tell us what is wrong and where you saw the right figure. Corrections are public and dated.
Report a correction on GitHub