Station 5 of 18 on Mumbai Metro Line 5, which will run from Thane through Bhiwandi to Kalyan, with a spur to Ulhasnagar. Elevated. Part of Phase 1, Kapurbawdi to Dhamankar Naka.

- Where
19.25983, 73.02794 (the built station on satellite imagery, Oct 2025)
See it on the mapOpenStreetMap (opens in a new tab)The drone flight past it, from 4:42
MMRDA's alignment file of March 2025, which puts it about 740 m north-east of the built station, beside the viaduct where it is single width put it 744 m from here.
- Along the line
Drawn from MMRDA's alignment file of March 2025 and the tentative key plan of March 2026, turned so Kapurbawdi is on the left. 8.7 km from the start of the line at Kapurbawdi
- Next stations
- Towards Thane: Kalher
- Towards Kalyan: Anjurphata
- Interchange
None announced
- Construction
Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs.
MMRDA's Line 5 page shows every civil activity 100% complete as of 31 Aug 2026 (verified) but does not name stations. The energisation covers Kapurbawdi to Dhamankar Naka.
- When it opens
No date has been announced for this station on its own. For Phase 1, Kapurbawdi to Dhamankar Naka, the target is Dec 2026.