Station 5 of 18 on Mumbai Metro Line 5, which will run from Thane through Bhiwandi to Kalyan, with a spur to Ulhasnagar. Elevated. Part of Phase 1, Kapurbawdi to Dhamankar Naka.

Drone view of Purna station's orange roof over the viaduct, among sheds with tin and tarpaulin roofs
The station among the warehouses around itDrone still from InfraUnfiltered's video (watch from 4:49), published
Where

19.25983, 73.02794 (the built station on satellite imagery, Oct 2025)

See it on the mapOpenStreetMap (opens in a new tab)The drone flight past it, from 4:42

MMRDA's alignment file of March 2025, which puts it about 740 m north-east of the built station, beside the viaduct where it is single width put it 744 m from here.

ReportedEsri Wayback (opens source in a new tab)

Along the line
Drawn from MMRDA's alignment file of March 2025 and the tentative key plan of March 2026, turned so Kapurbawdi is on the left.

8.7 km from the start of the line at Kapurbawdi

Next stations
Interchange

None announced

VerifiedMMRDA (opens source in a new tab)

Construction

Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs.

MMRDA's Line 5 page shows every civil activity 100% complete as of 31 Aug 2026 (verified) but does not name stations. The energisation covers Kapurbawdi to Dhamankar Naka.

ReportedFree Press Journal (opens source in a new tab)

When it opens

No date has been announced for this station on its own. For Phase 1, Kapurbawdi to Dhamankar Naka, the target is Dec 2026.

VerifiedMMRDA (opens source in a new tab)

Line 5 status and opening date, answered