Mumbai Metro Tracker

Every metro line in the Mumbai region. The unofficial tracker.

Edition of Facts checked Not affiliated with MMRDA

12A2B6797A451212ATR3N1
  • Running
  • Under construction
  • Approved, not started
  • Proposed

Every line

All 21 metro lines in the Mumbai region, from those being built to those only studied. The 8 lines this site tracks in full carry their tenders, funding and latest update, with a link to their own tracker.

Under construction 8

Line 2B

D N Nagar to Mandale

Stage
Mandale to Chembur open (six stations). Chembur to D N Nagar under construction: piers 99%, U and I girders 90% (MMRDA, 31 Aug 2026). Verified, source: MMRDA (opens in a new tab)
Target
2027 for Diamond Garden to Saraswat Nagar; a target, not an announced date Reported, source: Free Press Journal (opens in a new tab)
Authority
Mumbai Metropolitan Region Development Authority (MMRDA) Verified, source: MMRDA (opens in a new tab)
Cost
₹10,986 crore, project completion cost, including state taxes, 7.5% a year escalation and interest during construction Verified, source: MMRDA (opens in a new tab)
Funding
MMRDA for the civil works; the Asian Development Bank for the rest, as planned in 2016 Reported, source: Indian Infrastructure (opens in a new tab)
Tenders
8 traced; latest award CA-249 to Colossus Infra Projects, ₹33.95 cr, Jul 2024 Reported, source: The Metro Rail Guy (opens in a new tab)
Latest
13 Aug 2026: Phase IA opens: Chembur Verified, source: MMRDA (opens in a new tab)

Line 4

Wadala to Thane and Gaimukh

Stage
First stretch, Gaimukh to Cadbury Junction, built and in trial runs; RDSO certification on 2 Jun 2026; CMRS inspected the Gaimukh pit line and its report is awaited. The rest of the line is under construction. Reported, source: Free Press Journal (opens in a new tab)
Target
Dec 2026 for Phase 1; a target, not an announced date Reported, source: Free Press Journal (opens in a new tab)
Authority
Mumbai Metropolitan Region Development Authority (MMRDA) Verified, source: MMRDA (opens in a new tab)
Cost
₹14,549 crore, project base cost of Line 4, including taxes and duties Verified, source: MMRDA (opens in a new tab)
Funding
KfW (Germany) loans of EUR 545 million for the systems of Lines 4 and 4A; MMRDA funds the rest Verified, source: MMRDA (opens in a new tab)
Tenders
27 traced; latest award CA-298 to Larsen & Toubro, ₹1,260 cr, 24 Dec 2025 Reported, source: Metro Rail News (opens in a new tab)
Latest
14 Oct 2026: First of 39 driverless trains unveiled Reported, source: Railway Gazette (opens in a new tab)

Line 5

Thane to Kalyan

Stage
Phase 1 built and preparing for the CMRS safety inspection; overhead wires energised from 7 Sep 2026. Phase 2 and Phase 5A approved, not started. Reported, source: Free Press Journal (opens in a new tab)
Target
Dec 2026 for Phase 1; a target, not an announced date Verified, source: MMRDA (opens in a new tab)
Authority
Mumbai Metropolitan Region Development Authority (MMRDA) Verified, source: MMRDA (opens in a new tab)
Cost
₹18,130 crore, estimated cost of the expanded corridor, Phases 1, 2 and 5A Verified, source: MMRDA (opens in a new tab)
Funding
AIIB and OPEC Fund loans for the systems; MMRDA funds the rest Reported, source: The Metro Rail Guy (opens in a new tab)
Tenders
19 traced; latest award CA-241 to Titagarh Rail Systems, ₹2,481 cr, 31 Oct 2025 Verified, source: MMRDA (opens in a new tab)
Latest
7 Sep 2026: Overhead wires energised, Kapurbawdi to Dhamankar Naka Reported, source: Free Press Journal (opens in a new tab)

Line 6

Swami Samarth Nagar to Vikhroli

Stage
Under construction: piers 97.88%, U girders 93.40% erected, station works 87.35% (MMRDA, 31 Aug 2026). No stretch is open. Verified, source: MMRDA (opens in a new tab)
Target
2027 for the whole line; a target, not an announced date Reported, source: english.lokshahi.com (opens in a new tab)
Authority
Mumbai Metropolitan Region Development Authority (MMRDA) Verified, source: MMRDA (opens in a new tab)
Cost
₹6,716 crore, project completion cost Verified, source: MMRDA (opens in a new tab)
Funding
MMRDA, with a New Development Bank loan for the trains and systems Reported, source: The Metro Rail Guy (opens in a new tab)
Tenders
11 traced; latest award CA-233 (Systems Package 2) to IRCON International, ₹642.44 cr, 18 Jul 2025 Sources conflict, source: nbmcw.com (opens in a new tab)
Latest
17 Oct 2026: Footbridge tender for Vikhroli and Jogeshwari stations Verified, source: mahatenders.gov.in (opens in a new tab)

Line 7A

Andheri (E) to the airport

Stage
Under construction: viaduct and tunnels bored, airport station roof slab 64%, the short mined tunnels (NATM) not started (MMRDA, 31 Aug 2026). Work near Airport Colony is held up by an airport height limit (reported). Verified, source: MMRDA (opens in a new tab)
Target
2027 for the whole line; a target, not an announced date Reported, source: The Metro Rail Guy (opens in a new tab)
Authority
Mumbai Metropolitan Region Development Authority (MMRDA) Verified, source: MMRDA (opens in a new tab)
Cost
₹6,607 crore, project base cost of Lines 9 and 7A together, including state taxes and 7.5% a year escalation Verified, source: MMRDA (opens in a new tab)
Funding
Not published for 7A alone Reported, source: ummid.com (opens in a new tab)
Tenders
4 traced; latest award CA-176 to Leena Powertech-Umesh Brothers JV, Jun 2025 Reported, source: The Metro Rail Guy (opens in a new tab)
Latest
14 Jul 2025: Second tunnel breakthrough: bored tunnels complete Reported, source: The Metro Rail Guy (opens in a new tab)

Line 12

Kalyan to Taloja

Stage
Civil construction (viaduct and stations). Systems and rolling stock tender stage. Reported, source: MMRDA (opens in a new tab)
Target
May 2028; a target, not an announced date Sources conflict, source: Free Press Journal (opens in a new tab)
Authority
Mumbai Metropolitan Region Development Authority (MMRDA) Verified, source: MMRDA (opens in a new tab)
Cost
₹11,516 crore, estimated project cost, excluding interest during construction Sources conflict, source: MMRDA (opens in a new tab)
Funding
MMRDA is seeking a Rs 7,800 crore loan Verified, source: MMRDA (opens in a new tab)
Tenders
7 traced; latest award CA-240 to Gawar Constructions Ltd, ₹1,971.77 cr, 27 Mar 2024 Reported, source: The Metro Rail Guy (opens in a new tab)
Latest
31 Aug 2026: Progress snapshot: piles 37%, U-girders 19% Verified, source: MMRDA (opens in a new tab)

Thane Integral Ring Metro

Stage
Under construction: viaduct contract awarded Dec 2025, test pile May 2026, piling begun Nov 2026 (reported); station contracts not yet awarded Reported, source: @Sunny29223375 on X (opens in a new tab)
Target
Sep 2029 for the whole ring; a target, not an announced date Reported, source: Free Press Journal (opens in a new tab)
Authority
Maharashtra Metro Rail Corporation (MahaMetro) Verified, source: pib.gov.in (opens in a new tab)
Cost
₹12,200.1 crore, estimated cost of the project Verified, source: pib.gov.in (opens in a new tab)
Funding
Equal equity from the Government of India and the Government of Maharashtra, with part-funding from bilateral agencies Verified, source: pib.gov.in (opens in a new tab)
Tenders
12 traced; latest award T1-019/Consul-05/2025 to AECOM India and Nippon Koei India consortium, ₹179.85 cr, Jul 2026 Verified, source: Thane Ring Metro (official) (opens in a new tab)

Approved, not started 5

Line 8

Mumbai airport (CSMIA) to Navi Mumbai airport (NMIA)

Stage
  • Whole line: approved. State government resolution of 27 Jan 2025; CIDCO sent the project report to the state in Oct 2025. A Jan 2026 approval by the state's Cabinet Infrastructure Committee (Rs 22,862 crore) is reported but not checked. Union Cabinet approval pending Reported, source: oneindia.com (opens in a new tab)
Authority
CIDCO (nodal agency since Jan 2025, replacing MMRDA); to be built as a PPP Reported, source: Free Press Journal (opens in a new tab)

Line 10

Gaimukh to Shivaji Chowk (Mira Road)

Stage

Line 11

Bandra Terminus and Wadala to Gateway of India

Stage
Authority
Mumbai Metro Rail Corporation (MMRCL) Reported, source: Free Press Journal (opens in a new tab)

Line 12A

Manpada to Taloja via Kalyan Phata

Stage
Approved by the state Cabinet Infrastructure Committee on 27 Oct 2026; no tenders yet Reported, source: financialexpress.com (opens in a new tab)
Target
Apr 2030; a target, not an announced date Reported, source: financialexpress.com (opens in a new tab)
Authority
Mumbai Metropolitan Region Development Authority (MMRDA) Reported, source: financialexpress.com (opens in a new tab)
Cost
₹13,856.37 crore, project cost, with 15.62 km of integrated road flyovers Reported, source: financialexpress.com (opens in a new tab)
Funding
MMRDA, interest-free subordinate loans from the State, and loans from financial institutions Reported, source: Newsband (opens in a new tab)
Latest
27 Oct 2026: Cleared by the state Cabinet Infrastructure Committee Reported, source: financialexpress.com (opens in a new tab)

Line 13

Mira-Bhayandar to Virar

Stage

Proposed 2

Running 5

Studied as an idea 1

Network last checked 29 Oct 2026. Routes from MMRDA's alignment files, the Thane ring project's map and OpenStreetMap (Line 3, Navi Mumbai Line 1). A line with no published route is listed but not drawn. Stages are this site's reading of the sources; see the grade on each.

Latest updates

The newest milestones on the lines this site tracks in full, each linked to its report.

  1. Piling begins (opens in a new tab)Thane Integral Ring Metro · @Sunny29223375 on X Reported

  2. Cleared by the state Cabinet Infrastructure Committee (opens in a new tab)Line 12A · financialexpress.com Reported

  3. Footbridge tender for Vikhroli and Jogeshwari stations (opens in a new tab)Line 6 · mahatenders.gov.in Verified

  4. MahaMetro answers Thane on route and trees (opens in a new tab)Thane Integral Ring Metro · Free Press Journal Reported

  5. First of 39 driverless trains unveiled (opens in a new tab)Line 4 · Railway Gazette Reported

  6. Soil testing reaches Raila Devi (opens in a new tab)Thane Integral Ring Metro · @bodkeitis on X Reported

  7. Trial runs resume, Gaimukh to Cadbury Junction (opens in a new tab)Line 4 · Free Press Journal Reported

  8. Overhead wires energised, Kapurbawdi to Dhamankar Naka (opens in a new tab)Line 5 · Free Press Journal Reported

  9. Progress snapshot: piles 37%, U-girders 19% (opens in a new tab)Line 12 · MMRDA Verified

  10. Every civil activity shown 100% complete (opens in a new tab)Line 5 · MMRDA Verified

Where the lines meet

Stations where two tracked lines come together, measured between the two published station points.

Kalyan. Lines 12 and 5 both end by the railway junction. Line 5's Kalyan station is planned about 131 m from Line 12's Kalyan.

Kapurbawdi. Line 5 starts at a station built as part of Line 4. Line 4's Kapurbawdi point is 74 m from Line 5's Kapurbawdi.

Kanjurmarg. Line 6 crosses Line 4 on LBS Marg. Line 6's Kanjur Marg (W) point is 161 m from Line 4's Gandhi Nagar.