- When will Mumbai Metro Line 7A open?
MMRDA has announced no date. A trade press estimate of July 2025 puts the opening no sooner than the third quarter of 2027; the site counts down to the end of 2027. An earlier report's December 2026 will not be met: the short mined tunnels had not started by August 2026, and an airport height limit holds up part of the work.
ReportedThe Metro Rail Guy (opens source in a new tab)VerifiedMMRDA (opens source in a new tab)
- What is the Line 7A airport height problem?
Near Airport Colony, the elevated stretch and the ramp are lower than the overhead wire needs: the airport's permits of 2024 set heights up to about 2.4 m below the design. Work in that area stopped, and up to about Rs 250 crore of work may have to be rebuilt. MMRDA blamed its general consultant for not flagging the limit. On 8 Oct 2026 the Airports Authority of India was still making its final assessment. All as reported.
ReportedFree Press Journal (opens source in a new tab)ReportedRe-Mumbai (opens source in a new tab)
- How much of Line 7A is built?
MMRDA's table for 31 Aug 2026: the viaduct is complete and both bored tunnels are done. Left: the airport station (roof slab 64%), the cut and cover box (base slab 6%), the elevated ramp (95%) and the two short mined tunnels (0%).
- What is the route of Metro Line 7A?
Andheri (E) to the airport (CSIA), extending Line 7 from Gundavali. Sources give its length as 3.42 km or 3.17 km; MMRDA gives 2.195 km of it as underground. It continues Line 7 from Gundavali south along the Western Express Highway to Airport Colony, then goes under the airport to Terminal 2.
VerifiedMMRDA (opens source in a new tab)Sources conflictRe-Mumbai (opens source in a new tab)
- Which stations are on Line 7A?
2: Airport Colony (elevated) and CSIA (underground), at the airport's Terminal 2.
- Where does Line 7A meet other lines?
It continues Line 7 from Gundavali, so Line 7's trains are to run through to the airport. CSIA: Metro Line 3 (Aqua Line) at CSMIA T2, as reported.
- How much does Metro Line 7A cost?
MMRDA gives one cost for Lines 9 and 7A together: Rs 6,607 crore, including state taxes and escalation. For 7A alone, a report of August 2026 gives Rs 812 crore; the civil contract alone is reported at Rs 1,998 crore. No MMRDA figure for 7A alone was found.
VerifiedMMRDA (opens source in a new tab)ReportedThe Metro Rail Guy (opens source in a new tab)
- Who is building Line 7A?
MMRDA. J Kumar Infraprojects holds the civil contract (CA-48, Sep 2019): viaduct, ramp, tunnels and both stations. Its two tunnel boring machines, Disha and Dhruv, finished in April and July 2025. Power and overhead wire for Lines 9 and 7A: the Leena Powertech-Umesh Brothers JV (CA-176). All as reported.
VerifiedMMRDA (opens source in a new tab)ReportedThe Metro Rail Guy (opens source in a new tab)ReportedThe Metro Rail Guy (opens source in a new tab)
- How many people will use Line 7A?
MMRDA gives one figure for Lines 9 and 7A together: about 11.12 lakh riders a day by 2031. No figure for 7A alone.
- What else is Metro Line 7A called?
Mumbai Metro Line 7A is also called Metro 7A, Line 7 extension, Andheri-Airport Metro. MMRDA calls it the extension of Line 7, whose colour is Red.