Line 5

Mumbai Metro, Thane to Kalyan. The unofficial tracker.

All linesEdition of Facts checked Not affiliated with MMRDA

Watch Mumbai Metro Line 5 reach Kalyan,
phase by phase.

Phase 1, from Kapurbawdi in Thane to Dhamankar Naka in Bhiwandi, is built: on 31 Aug 2026, MMRDA's progress table showed every civil activity complete. Phases 2 and 3 take the line on to Kalyan, with a spur to Ulhasnagar: 19 stations in all, as MMRDA counts them.

VerifiedMMRDA (opens source in a new tab)

Ride the line
Isometric drawing of the Line 5 bridge over Kasheli creek: concrete piers on pile caps carry a box-girder deck high over the water, and a six-car train runs on top. The number 5 is painted on the bank.5
The Kasheli creek bridge, between Balkum Naka and Kasheli: 550 m long, in spans of 42.23 m, about 15 m above the water, as reported. Illustration, not to scale; not an official design.
KapurbawdiKalyanUlhasnagar18 stations34.21 km. Ride the line.

Route

Eighteen stations, Kapurbawdi to Kalyan, and the Line 5A spur to Ulhasnagar. Scroll to ride the line station by station. Distances follow MMRDA's alignment file of March 2025 to the Ulhas river bridge, and the tentative key plan of March 2026 past it.

  1. Kapurbawdi

    Station 1 of 18

    0.41 km from the start of the line at Kapurbawdi Reportedopenstreetmap.org (opens source in a new tab)

    Change for Metro Line 4 (Wadala-Kasarvadavali)VerifiedMMRDA (opens source in a new tab)

    Built as part of Metro Line 4; shared by Lines 4 and 5 Verified

    Line 5's first station and its interchange with Line 4. It is built under Line 4's contracts, so MMRDA does not count it among Line 5's stations; the site lists it as Line 5's station 1 (owner's decision, 2026-10-09). Not in the 15-station list on MMRDA's Line 5 page.

  2. Balkum Naka

    Station 2 of 18

    2.27 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    • The Thane Integral Ring Metro's own Balkum Naka station is about 1 km east, on Balkum Pipeline Road near Balkum Road, on that project's official route map; the same map puts this station within 18 m of MMRDA's point VerifiedThane Ring Metro (official) (opens source in a new tab)

    Planned interchange: Thane Integral Ring Metro (Maha-Metro) Reportedhousing.com (opens source in a new tab)

    Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported

  3. Kasheli

    Station 3 of 18

    5.97 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported

  4. Kalher

    Station 4 of 18

    7.86 km from the start of the line at Kapurbawdi ReportedEsri Wayback (opens source in a new tab)

    Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported

  5. Purna

    Station 5 of 18

    8.69 km from the start of the line at Kapurbawdi ReportedEsri Wayback (opens source in a new tab)

    Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported

  6. Anjurphata

    Station 6 of 18

    10.95 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported

  7. Dhamankar Naka

    Station 7 of 18

    12.58 km from the start of the line at Kapurbawdi ReportedEsri Wayback (opens source in a new tab)

    Built. Overhead wires energised from 7 Sep 2026, ahead of trial runs. Reported

  8. Bhiwandi

    Station 8 of 18

    13.71 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    Underground station

    Not started Reported

    Underground in the revised plan (MMRDA, May 2026); MMRDA's 2025 alignment file still places it on the 2017 route.

  9. Temghar

    Station 9 of 18

    16.15 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    Not started Reported

  10. Rajnouli

    Station 10 of 18

    17.94 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    Not started Reported

  11. Gove Gaon

    Station 11 of 18

    18.96 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    Not started Reported

  12. Kon Gaon

    Station 12 of 18

    21.26 km from the start of the line at Kapurbawdi VerifiedMMRDA (opens source in a new tab)

    Not started Reported

  13. Kongaon West

    Station 13 of 18

    Position not published UnverifiedMMRDA (opens source in a new tab)

    Not started Reported

    New in the revised plan. Its order is MMRDA's list order; whether it lies before or after Kon Gaon on the ground is not published. Other reports call the two stations Kongan West and Kongan East.

  14. Durgadi

    Station 14 of 18

    23.15 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)

    Not started Reported

    Called Durgadi Fort in MMRDA's 2025 alignment file, at a different place on the 2017 route.

  15. Khadakpada

    Station 15 of 18

    24.66 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)

    Not started Reported

    Near Khadakpada Circle, on Khadakpada Road.

  16. Bhoirwadi

    Station 16 of 18

    25.93 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)

    Not started Reported

  17. Shivaji Path

    Station 17 of 18

    27.89 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)

    Not started Reported

    MMRDA's press release calls it Chhatrapati Shivaji Maharaj Path.

  18. Kalyan

    Station 18 of 18

    29.16 km from the start of the line at Kapurbawdi Reported@Maha7Arindam on X (opens source in a new tab)

    Change for Metro Line 12 (Kalyan-Taloja),Central Railway (Kalyan Junction)VerifiedMMRDA (opens source in a new tab)

    Not started Reported

    The end of Phase 3. In the key plan it sits 131 m from Line 12's Kalyan station, north of Kalyan railway station; in MMRDA's 2025 file it was 14 m from it.

A hollow line marks track that is not yet open, and a dashed outline the underground stretch. No part of Line 5 has opened.

Line 5A spur, from Bhoirwadi

  1. Shanti Nagar

    2.05 km along the spur Reported@Maha7Arindam on X (opens source in a new tab)

    Not started Reported

    About 500 m from Vithalwadi railway station.

  2. Shivaji Chowk

    3.43 km along the spur Reported@Maha7Arindam on X (opens source in a new tab)

    Not started Reported

    MMRDA's press release calls it Chhatrapati Shivaji Maharaj Chowk.

  3. Ulhasnagar

    4.68 km along the spur Reported@Maha7Arindam on X (opens source in a new tab)

    Not started Reported

    The end of the spur. In the key plan it lies about 1.1 km east of Ulhasnagar railway station; MMRDA's press release promises direct access to that station, which the key plan does not show.

Map

The line on a street map. Choose a station to see where it sits, what surrounds it and what the street looks like today. The route to the Ulhas river bridge comes from MMRDA's alignment file of March 2025; Phase 3 and the spur come from the tentative key plan of March 2026.

Route not yet open: MMRDA's alignment file, then the tentative key planVerifiedMMRDA (opens source in a new tab)

Underground stretch, route below ground not published

Kapurbawdi

19.22414, 72.97742 (OpenStreetMap, checked on satellite imagery)

Choose a station on the map or in the list.

Street level

The street view for the chosen station appears here.

Station data last reviewed 9 Oct 2026.

Before and after

The same spots from above, before construction began in January 2020 and in the latest imagery. Drag the handle or use the arrow keys to compare.

The latest image is Esri's newest of this area, captured . The site checks for newer imagery every month; last checked .

Oct 2018Oct 2025
Kapurbawdi, from above. Before: captured 24 Oct 2018 (Maxar). After: captured 12 Oct 2025 (Vantor). Imagery: Esri World Imagery Wayback.VerifiedEsri Wayback (opens source in a new tab)Centred on the station's position: OpenStreetMap, checked on satellite imagery.

From the air

A drone flight along Phase 1, from Dhamankar Naka to Kapurbawdi, by InfraUnfiltered, published . Shared with permission. Pick a station to start the video where the flight reaches it.

The video loads from YouTube only when you press play.

Numbers

The line in figures. Old figures stay on the page, struck through, so you can see how the project changed.

Length
34.21km with the spur; Bhiwandi underground
22.38 km Line 5 before Phase 5A was added, Kapurbawdi to Durgadi24.9 km 2017 plan, Thane to Kalyan APMC, fully elevated
VerifiedMMRDA (opens source in a new tab)
Stations
19as MMRDA counts them, without Kapurbawdi
15 2017 plan, Balkum Naka to Kalyan APMC (still on MMRDA's Line 5 page)17 Station points in MMRDA's 2025 alignment file, counting Kapurbawdi
VerifiedMMRDA (opens source in a new tab)
Estimated cost
18,130crore rupees, Phases 1, 2 and 5A
₹8,416.51 crore 2017 plan, 24.9 km, including land and taxesPhase 1 ₹6,741 crore, Phase 2 ₹7,326 crore, Phase 5A (Phase 3 and the spur) ₹4,063 crore, MMRDA, May 2026.
VerifiedMMRDA (opens source in a new tab)
Funding
Loans for the systems
In April 2020 AIIB approved a loan concept of USD 236 million for the trains, signalling and power, with the OPEC Fund planned to lend too; MMRDA funds the rest. The final loan amounts are not published.
ReportedThe Metro Rail Guy (opens source in a new tab)
Daily riders by 2031
3.025lakh a day (projected)
VerifiedMMRDA (opens source in a new tab)
Depot
Kasheli27.134 ha
Kon (MIDC) or APMC Kalyan earlier options, both on Phase 2
VerifiedMMRDA (opens source in a new tab)
Interchanges
  • Kapurbawdi for Metro Line 4 (Wadala-Kasarvadavali)
  • Kalyan for Metro Line 12 (Kalyan-Taloja) and the Central Railway at Kalyan Junction
VerifiedMMRDA (opens source in a new tab)
Planned: Balkum Naka for the Thane Integral Ring Metro (Maha-Metro), due by 2029. Reportedhousing.com (opens source in a new tab)
Travel time
40 to 50% shorterthan by road (MMRDA, 2026). Its Line 5 page still says 50 to 75%.
Sources conflictMMRDA (opens source in a new tab)

What changed since 2017

MMRDA's Line 5 page still shows the plan of 2017. The revised plan of 2026 takes the line past Durgadi in a loop to Kalyan, adds a spur to Ulhasnagar and puts Bhiwandi station underground. Here is what changed, figure by figure and station by station.

The 2017 plan against the plan of 2026
Fact2017 plan2026 plan
RouteThane to Kalyan APMC, via BhiwandiThane (Kapurbawdi) to Kalyan, via Bhiwandi and Durgadi, with a spur from Bhoirwadi to Ulhasnagar VerifiedMMRDA (opens source in a new tab)
Length24.9 km34.21 km, with the spur VerifiedMMRDA (opens source in a new tab)
Stations1519, as MMRDA counts them VerifiedMMRDA (opens source in a new tab)
BuiltAll elevatedElevated, except Bhiwandi station (underground) Sources conflictMMRDA (opens source in a new tab)

2017 plan: VerifiedMMRDA (opens source in a new tab)

The 15 stations of 2017

12 kept, 3 not in the 2026 plan.

  1. Balkum NakaKept on Phase 1
  2. KasheliKept on Phase 1
  3. KalherKept on Phase 1
  4. PurnaKept on Phase 1
  5. AnjurphataKept on Phase 1
  6. Dhamankar NakaKept on Phase 1, its last station
  7. BhiwandiKept on Phase 2, now underground
  8. Gopal NagarDropped. Not in MMRDA's revised station list.
  9. TemgharKept on Phase 2
  10. RajnouliKept on Phase 2, as Rajnoli
  11. Gove GaonKept on Phase 2
  12. Kon GaonKept on Phase 2
  13. Lal ChowkiNot in the 2026 list. MMRDA's 2025 alignment file has no Lal Chowki; it has Durgadi Fort and Sahajanand Chowk on this stretch.
  14. Kalyan Station now KalyanKept: the end of Phase 3, at the Line 12 interchange
  15. Kalyan APMCDropped. Not in MMRDA's revised station list.

New since 2017

9 stations that the 2017 plan did not have.

  1. KapurbawdiPhase 1, built as part of Metro Line 4
  2. Kongaon WestPhase 2
  3. DurgadiPhase 3
  4. KhadakpadaPhase 3
  5. BhoirwadiPhase 3
  6. Shivaji PathPhase 3
  7. Shanti NagarLine 5A spur
  8. Shivaji ChowkLine 5A spur
  9. UlhasnagarLine 5A spur

2026 plan: VerifiedMMRDA (opens source in a new tab)

See both routes on the map: tick "Show the earlier plan's route and dropped stations". The map draws MMRDA's 2025 file of the earlier route.

Progress

MMRDA publishes one progress table for Line 5, updated monthly. It does not say which stretch the table covers; its items match Phase 1, the only part being built. It does not publish progress by station.

Phase 1, Kapurbawdi to Dhamankar Naka

  1. PlanningDoneApproved, 2017
  2. Tenders and designDoneCivil contract awarded, 7 Jan 2020
  3. Civil constructionDoneEvery civil activity complete, 31 Aug 2026
  4. Systems and trainsNowOverhead wires energised, 7 Sep 2026 (reported)
  5. Testing and safety approvalNot startedPreparing for the safety inspection (reported). No date announced
  6. OpeningNot startedTarget end of 2026, MMRDA

Phase 2, Dhamankar Naka to Durgadi

  1. PlanningDoneUnion approval, 29 Aug 2026 (reported)
  2. Tenders and designNot startedNo tender reported yet
  3. Civil constructionNot startedWork beyond Bhiwandi has not begun (reported)
  4. Systems and trainsNot startedNo date announced
  5. Testing and safety approvalNot startedNo date announced
  6. OpeningNot startedReported target 2030-31

Phase 3 and the Line 5A spur, Durgadi to Kalyan and Ulhasnagar

  1. PlanningDoneUnion approval, 29 Aug 2026 (reported)
  2. Tenders and designNot startedConsultant tender cancelled, 19 Aug 2026 (reported)
  3. Civil constructionNot startedWork beyond Bhiwandi has not begun (reported)
  4. Systems and trainsNot startedNo date announced
  5. Testing and safety approvalNot startedNo date announced
  6. OpeningNot startedReported target 2030-31

Civil works complete, as of

100%

Every activity in MMRDA's table, 9 of 9:

  • Piling works (viaduct and station)
  • Pile cap works
  • Pier works
  • Cast-in-situ pier caps
  • Pier cap erection (viaduct)
  • U-girder erection (viaduct)
  • Station spine erection
  • Station wings erection
  • Deck slab

VerifiedMMRDA (opens source in a new tab)

Tenders and contracts

Every package we could trace, with its value in crore rupees. MMRDA keeps only current notices online, so most of these come from trade press.

PackageScopeFloatedEstimateAwardedAwarded toStatusSource
CA-28Part design and construction of the viaduct and stations from Kapurbawdi to Dhamankar Naka, 12.811 kmJan 2019Not publishedNot published7 Jan 2020Afcons InfrastructureAwardedReportedThe Metro Rail Guy (opens source in a new tab)
CA-151Kasheli depot: stabling yard, sheds, workshops, operation control centre, administrative building and staff quartersOct 2022₹472.02 cr₹589.56 cr14 Sep 2023Rithwik ProjectsAwardedReportedThe Metro Rail Guy (opens source in a new tab)
CA-159Supply of about 6,800 t of head-hardened rails for Lines 5 and 9Not foundNot publishedNoneNoneCancelledReportedThe Metro Rail Guy (opens source in a new tab)
CA-166Ballastless standard-gauge track from Kapurbawdi to Dhamankar Naka (Phase 1) and the depot line near KasheliNot foundNot published₹97.4 crParas RailtechAwardedReportedThe Metro Rail Guy (opens source in a new tab)
CA-203Supply of about 6,800 t of head-hardened rails for Lines 5 and 9 (second call after CA-159)Not foundNot publishedNoneNoneCancelledReportedThe Metro Rail Guy (opens source in a new tab)
CA-219General consultant for Phase 2, Bhiwandi to KalyanNot foundNot publishedNoneNoneCancelledReportedThe Metro Rail Guy (opens source in a new tab)
CA-239Overhead electrification, power supply, traction, electrical and mechanical works, lifts and escalatorsFeb 2024Not publishedNot yetNot yetBids openedReportedThe Metro Rail Guy (opens source in a new tab)
CA-241Rolling stock (22 six-car trains), CBTC signalling and train control, telecom, platform screen doors, and depot machinery at KasheliFeb 2024₹2,640.72 cr₹2,481 cr31 Oct 2025Titagarh Rail SystemsAwardedVerifiedMMRDA (opens source in a new tab)
CA-242Automatic fare collection for Phases 1 and 2, with 15 years of maintenance after a 2-year defect period20 Mar 2024Not publishedNot foundNot foundUnknownVerifiedaiib.org (opens source in a new tab)
CA-246Architectural finishing and pre-engineered steel at the 6 elevated Phase 1 stationsNot foundNot publishedNot publishedNACPL-Mansi-UCC JVAwardedReportedThe Metro Rail Guy (opens source in a new tab)
CA-256General consultant for Phase 2, Dhamankar Naka to Kalyan APMC (13.02 km of viaduct, including 3.5 km underground; the 2023 plan)2024Not publishedNot foundNot foundUnknownReportedThe Metro Rail Guy (opens source in a new tab)
MMI worksMulti-modal integration facilities at the 6 Phase 1 stations, Balkum Naka to Dhamankar NakaJun 2024Not published₹52.33 cr4 Dec 2024K R ConstructionAwardedVerifiedmahatenders.gov.in (opens source in a new tab)
MMI consultantProject management consultant to supervise and monitor the multi-modal integration works at the 6 Phase 1 stationsAug 2024Not published₹1.35 cr22 Sep 2025Dhruv Consultancy ServicesAwardedVerifiedmahatenders.gov.in (opens source in a new tab)
CA-311Signage graphics and station furniture (design, supply, installation, testing and commissioning) at the six elevated Phase 1 stationsApr 2026Not publishedNot yetNot yetOpenReported@MH04Thane on X (opens source in a new tab)
CA-303Standard-gauge track work (ballasted and ballastless) at the Kasheli depotJun 2026₹84.35 crNot foundNot foundUnknownReportedFree Press Journal (opens source in a new tab)
CA-293General consultant for the civil works of Line 5A (Durgadi to Kalyan with a spur to Ulhasnagar), 48 monthsSep 2025Not publishedNoneNoneCancelledVerifiedmahatenders.gov.in (opens source in a new tab)
CA-317Phase 2, Dhamankar Naka to Rajnoli Junction (ch. 12,200 to 17,860): design and construction of the viaduct, cut and cover, open ramp and tunnel, with 1 underground and 1 elevated station (excluding architectural finishing and pre-engineered steel)29 Oct 2026Not publishedNot yetNot yetOpenVerifiedmahatenders.gov.in (opens source in a new tab)
CA-318Phase 2 and Phase 3, Rajnoli Junction to Bhoirwadi (ch. 17,860 to 26,140): design and construction of the elevated viaduct, the viaduct integrated with a road flyover, a creek bridge, connecting road ramps and 7 elevated stations (excluding architectural finishing)30 Oct 2026Not publishedNot yetNot yetOpenVerifiedmahatenders.gov.in (opens source in a new tab)
CA-314Line 5A. Part A (ch. 3,596 to 6,521 of Phase 3): elevated viaduct and 1 elevated station. Part B (ch. 383 to 5,272 of the spur): elevated viaduct with an integrated road flyover and 3 double-decker elevated stations30 Oct 2026Not publishedNot yetNot yetOpenVerifiedmahatenders.gov.in (opens source in a new tab)

Who is building it

Trains

The trains are ordered. Titagarh Rail Systems is building 22 six-car trains for Phases 1 and 2, with the signalling, platform screen doors and depot machinery, under one contract announced on 31 Oct 2025.

Render of an orange and silver Titagarh metro train with a black front and a blue and green stripe, car D6A001, on an elevated track.
Titagarh's render of its Mumbai Metro train. Titagarh builds the trains for Lines 5 and 6 and does not say which line this shows; the car number, D6A001, may point to Line 6. Image: Titagarh Rail Systems. Unverifiedtitagarh.in (opens source in a new tab)22 trains of 6 cars are ordered for Line 5 (package CA-241).

Titagarh Rail SystemsReportedFree Press Journal (opens source in a new tab)

Package CA-241, ₹2,481 crore: 22 trains of 6 cars (132 coaches), built at its plant at Uttarpara, near Kolkata. To be commissioned within 217 weeks. ReportedFree Press Journal (opens source in a new tab)

Maintenance: Five years of comprehensive maintenance in the award reports; the tender set 15 years after a 2-year defect liability period. Sources conflictFree Press Journal (opens source in a new tab)

Traction, from ABB India: Traction and train control (TCMS) for the 22 trains, on 25 kV AC overhead power; automation at grade GoA2, upgradable to GoA4. Reportedmachinist.in (opens source in a new tab)

Cars per train
6
Trains
22
Car width
3.20 m
Car height
3.90 m
Length
21.84 m
Capacity, 6 cars
1,756 people

MMRDA's published figures. MMRDA's Line 5 page lists width, height and length under rolling stock; it does not say whether the length is one car or a whole train, so the page shows it as given. Trains and cars per train come from the contract. VerifiedMMRDA (opens source in a new tab)

Stations

All 18 on the line, in order from Kapurbawdi, then the three on the Line 5A spur and the three the 2017 plan had. Names follow MMRDA. Select a station to ride to it, or open its own page.

  1. 01KapurbawdiInterchange: Metro Line 4 (Wadala-Kasarvadavali)Same site as Line 4 KapurbawdiStation page: Kapurbawdi
  2. 02Balkum Nakaबाळकुम नाकाPlanned interchange: Thane Integral Ring Metro (Maha-Metro)Station page: Balkum Naka
  3. 03KasheliकशेलीStation page: Kasheli
  4. 04Kalherकाल्हेरStation page: Kalher
  5. 05Purnaपूर्णाStation page: Purna
  6. 06AnjurphataअंजुरफाटाStation page: Anjurphata
  7. 07Dhamankar Nakaधामणकर नाकाStation page: Dhamankar Naka
  8. 08BhiwandiभिवंडीUndergroundStation page: Bhiwandi
  9. 09TemgharटेमघरStation page: Temghar
  10. 10RajnouliरजनोलीStation page: Rajnouli
  11. 11Gove Gaonगोव गावStation page: Gove Gaon
  12. 12Kon Gaonकोन गावStation page: Kon Gaon
  13. 13Kongaon WestPosition not yet mappedStation page: Kongaon West
  14. 14DurgadiStation page: Durgadi
  15. 15KhadakpadaStation page: Khadakpada
  16. 16BhoirwadiStation page: Bhoirwadi
  17. 17Shivaji PathStation page: Shivaji Path
  18. 18Kalyanकल्याण स्टेशनInterchange: Metro Line 12 (Kalyan-Taloja), Central Railway (Kalyan Junction)Same site as Line 12 KalyanStation page: Kalyan

Line 5A spur, from Bhoirwadi

  1. 01Shanti NagarStation page: Shanti Nagar
  2. 02Shivaji ChowkStation page: Shivaji Chowk
  3. 03UlhasnagarStation page: Ulhasnagar

On the 2017 plan, dropped in the revised plan

Station list and order ReportedMMRDA (opens source in a new tab) station count VerifiedMMRDA (opens source in a new tab)

Updates

The latest reported milestones, each linked to the article or document, posts on X picked by hand, and news that a script finds every six hours.

On X

Posts by people who follow the project, not by MMRDA. Their claims count as reported.

  1. Better Thane @MH04Thane

    MMRDA has floated a tender for signage graphics and station furniture at the six elevated stations of Metro Line 5, Thane-Bhiwandi-Kalyan. Its drawings show the station signs, such as Balkum Naka's, numbered 501, on an orange band.

Timeline

From the first report in 2017 to the reported opening target. Dates show only as much precision as the source gives.

  1. Line 5 approved: 24.9 km, 17 stations

    The original plan for a fully elevated Thane-Bhiwandi-Kalyan line is approved at Rs 8,416.51 crore.

    ApprovalReportedMetro Rail News (opens source in a new tab)

  2. Bids invited for the Thane-Bhiwandi civil works

    MMRDA invites bids for package CA-28, the viaduct and stations from Kapurbawdi to Dhamankar Naka.

    TenderReportedThe Metro Rail Guy (opens source in a new tab)

  3. Afcons wins the Thane-Bhiwandi civil contract

    MMRDA awards package CA-28, 12.811 km from Kapurbawdi to Dhamankar Naka, to Afcons Infrastructure.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  4. AIIB approves a loan concept for Line 5's systems

    A USD 236 million loan for trains, signalling and other systems, alongside the OPEC Fund and MMRDA.

    PlanningReportedThe Metro Rail Guy (opens source in a new tab)

  5. MMRDA publishes the Phase 1 environmental report

    Prepared for AIIB: 11.88 km and six stations from Kapurbawdi to Dhamankar Naka, with the depot at Kasheli.

    PlanningVerifiedMMRDA (opens source in a new tab)

  6. Rithwik Projects wins the Kasheli depot contract

    Package CA-151, Rs 589.56 crore, for the depot's yards, sheds, workshops and control centre on about 27 ha.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  7. Titagarh is the lowest bidder for the trains and signalling

    Package CA-241, against MMRDA's estimate of Rs 2,640.72 crore from the February 2024 bid invitation.

    TenderReportedThe Metro Rail Guy (opens source in a new tab)

  8. Titagarh gets the trains and signalling contract

    Package CA-241, Rs 2,481 crore: 22 six-car trains built near Kolkata, CBTC signalling, telecom, platform screen doors and depot machinery, for Phases 1 and 2. Titagarh announced MMRDA's letter of acceptance to the stock exchanges.

    AwardReportedFree Press Journal (opens source in a new tab)

  9. Phase 1 civil work 95% complete

    MMRDA says the Kapurbawdi to Dhamankar Naka stretch is 95% built and aims to open it in December 2026.

    ConstructionReportedFree Press Journal (opens source in a new tab)

  10. Consultant tender for Phase 3 and the Ulhasnagar spur

    MMRDA invites bids for a general consultant for 'Metro Line 5A Durgadi to Kalyan with spur to Ulhasnagar'. Its documents show a tentative route.

    TenderReported@Maha7Arindam on X (opens source in a new tab)

  11. State approves the revised Line 5 and Line 5A

    34.2 km in all, from Thane through Bhiwandi and Durgadi to Kalyan, with an extension towards Ulhasnagar.

    ApprovalReportedIndian Infrastructure (opens source in a new tab)

  12. MMRDA sets out the expanded 34.21 km corridor

    Phase 1 to Dhamankar Naka, Phase 2 to Durgadi with Bhiwandi underground, and Phase 5A to Kalyan with a spur to Ulhasnagar; Phase 1 prepares for the CMRS inspection.

    PlanningVerifiedMMRDA (opens source in a new tab)

  13. That consultant tender is cancelled

    Cancelled by a notice dated 19 Aug 2026, ten days before the Union approval.

    TenderReported@Maha7Arindam on X (opens source in a new tab)

  14. Union Government approves Phases 2 and 3 and Line 5A

    Phase 2, Dhamankar Naka to Durgadi (10.48 km); Phase 3, Durgadi to Kalyan (11.82 km); and Line 5A, the Bhoirwadi to Ulhasnagar spur (5.27 km). MMRDA is to call tenders.

    ApprovalReported@bodkeitis on X (opens source in a new tab)

  15. Every civil activity shown 100% complete

    MMRDA's progress table lists piling, piers, girders, station spines, wings and deck slabs as complete.

    ConstructionVerifiedMMRDA (opens source in a new tab)

  16. Overhead wires energised, Kapurbawdi to Dhamankar Naka

    MMRDA powers 12.6 km of 25,000-volt wires, and the Kasheli depot tracks, ahead of trial runs.

    ConstructionReportedFree Press Journal (opens source in a new tab)

  17. Target: Phase 1 opens

    Reported target for passenger service from Kapurbawdi to Dhamankar Naka, after trial runs and safety approval.

    Still to comeReportedFree Press Journal (opens source in a new tab)

  18. Target: Phases 2 and 3, and Line 5A

    Reported target of 2030-31 for Line 5 beyond Dhamankar Naka and for the Line 5A spur to Ulhasnagar.

    Still to comeReportedMetro Rail News (opens source in a new tab)

Sources and corrections

Every figure on this page links to where it came from. This is how to read the marks next to them.

  • Verified Confirmed by MMRDA or its published project report.
  • Reported From a news or trade source, not confirmed by MMRDA.
  • Unverified Could not be confirmed. Treat with care.
  • Sources conflict Sources disagree. Alternatives are shown.

Primary sources

The full list, with every news and trade source, is in SOURCES.md.

Spotted a mistake?

Tell us what is wrong and where you saw the right figure. Corrections are public and dated.

Report a correction on GitHub