Line 2B

Mumbai Metro, D N Nagar to Mandale. The unofficial tracker.

All linesEdition of Facts checked Not affiliated with MMRDA

Follow Mumbai Metro Line 2B
from Mandale to D N Nagar.

Six stations are open, from Mandale through Mankhurd to Chembur. The other fourteen, from Chembur through Kurla, BKC and Bandra to D N Nagar, are being built: on 31 Aug 2026, MMRDA put pier work at about 99 per cent and girder work at about 90 per cent. 20 stations in all.

VerifiedMMRDA (opens source in a new tab)

Ride the line
ESIC NagarMandale Metro20 stations23.643 km. Ride the line.

Riding the line

The opening date, train times, how often trains run and what a ticket costs. Each fact shows once MMRDA or a news source gives it, with its source.

Phase I, Mandale to Diamond Garden

Open since 7 Apr 2026. VerifiedMMRDA (opens source in a new tab)

MMRDA: operational from 7 Apr 2026. Inaugurated that day by the Chief Minister; open to riders from 8 Apr (Free Press Journal).

First and last train
6:00 am to 10:30 pm
At the opening, 7 Apr 2026: 'from 6 am to 10:30 pm'. A route guide gives 10 pm for the last train. Check Maha Mumbai Metro for today's timetable.
ReportedFree Press Journal (opens source in a new tab)
A train every
9.5 min all day
About nine and a half minutes all day, 209 trips a day, at the opening (Free Press Journal, 7 Apr 2026). The report gives one interval for the whole day, no peak and off-peak split.
ReportedFree Press Journal (opens source in a new tab)
Single fare
₹10 to ₹20
At the opening: Rs 10 from Mandale to Deonar (BSNL Metro), Rs 20 for the whole stretch to Diamond Garden (Free Press Journal, 7 Apr 2026).
ReportedFree Press Journal (opens source in a new tab)

Phase IA, Diamond Garden to Chembur

Open since 13 Aug 2026. VerifiedMMRDA (opens source in a new tab)

MMRDA: Phase IA, 0.29 km with one station, operational from 13 Aug 2026. Services began at 5 pm that day (Free Press Journal).

Chembur to D N Nagar

Not open yet. No opening date announced.

Route

Twenty stations, ESIC Nagar to Mandale. Scroll to ride the line station by station. Distances follow MMRDA's alignment file of March 2025, from ESIC Nagar.

  1. ESIC Nagar

    Station 1 of 20

    0.00 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  2. Prem Nagar

    Station 2 of 20

    1.14 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  3. Indira Nagar

    Station 3 of 20

    1.69 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  4. Nanavati Hospital

    Station 4 of 20

    2.81 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  5. Khira Nagar

    Station 5 of 20

    4.39 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  6. Saraswat Nagar

    Station 6 of 20

    5.38 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  7. National College

    Station 7 of 20

    6.43 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  8. Bandra Metro

    Station 8 of 20

    7.56 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Change for Western Railway suburban, BandraReportedoneindia.com (opens source in a new tab)

    Under construction Verified

  9. Income Tax Office

    Station 9 of 20

    9.68 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Change for Metro Line 3 (Aqua Line)Reportedoneindia.com (opens source in a new tab)

    Under construction Verified

  10. ILFS

    Station 10 of 20

    11.16 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  11. MTNL Metro

    Station 11 of 20

    11.94 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  12. SG Barve Marg

    Station 12 of 20

    13.69 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  13. Kurla (E)

    Station 13 of 20

    15.34 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Change for Central Railway suburban, KurlaReportedoneindia.com (opens source in a new tab)

    Under construction Verified

  14. EEH

    Station 14 of 20

    16.37 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Under construction Verified

  15. Chembur

    Station 15 of 20

    16.93 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Change for Central Railway Harbour line, Chembur (about 200 m),Mumbai Monorail, V N Purav Marg (about 100 m)Reportedbusinesstoday.in (opens source in a new tab)

    Open since 13 Aug 2026 VerifiedMMRDA (opens source in a new tab)

  16. Diamond Garden

    Station 16 of 20

    17.90 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Open since 7 Apr 2026 VerifiedMMRDA (opens source in a new tab)

  17. Shivaji Chowk

    Station 17 of 20

    18.64 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Open since 7 Apr 2026 VerifiedMMRDA (opens source in a new tab)

  18. BSNL Metro

    Station 18 of 20

    19.84 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Open since 7 Apr 2026 VerifiedMMRDA (opens source in a new tab)

  19. Mankhurd

    Station 19 of 20

    21.38 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Change for Central Railway Harbour line, MankhurdReportedoneindia.com (opens source in a new tab)

    Open since 7 Apr 2026 VerifiedMMRDA (opens source in a new tab)

  20. Mandale Metro

    Station 20 of 20

    22.40 km from the start of the line at ESIC Nagar VerifiedMMRDA (opens source in a new tab)

    Open since 7 Apr 2026 VerifiedMMRDA (opens source in a new tab)

A solid line marks track open to riders, Mandale to Chembur; a hollow line marks track under construction.

Map

The line on a street map. Choose a station to see where it sits, what surrounds it and what the street looks like today. The route and stations come from MMRDA's alignment file of March 2025.

Route, MMRDA's alignment file; open from Mandale to ChemburVerifiedMMRDA (opens source in a new tab)

Chembur

19.05393, 72.89264 (MMRDA's alignment file, Mar 2025)

Choose a station on the map or in the list.

Street level

The street view for the chosen station appears here.

Station data last reviewed 30 Oct 2026.

Numbers

The line in figures. Old figures stay on the page, struck through, so you can see how the project changed.

Length
23.643km, fully elevated, from D N Nagar
23.5 km At the foundation stone, Dec 2016
VerifiedMMRDA (opens source in a new tab)
Stations
20all elevated; MMRDA also says 19
22 When MMRDA approved the draft plan, May 2016 (Indian Infrastructure)21 Points in MMRDA's alignment file (March 2025): the 20 listed and Kurla Terminus, which the list no longer has
Sources conflictMMRDA (opens source in a new tab)
Estimated cost
10,986crore rupees, with taxes, escalation and interest
₹10,970 crore Total cost when MMRDA approved the draft plan, May 2016: Rs 109.7 billionMMRDA's Line 2B page, the figure of the project report approved in 2016. No revised cost was found.
VerifiedMMRDA (opens source in a new tab)
Funding
MMRDA and ADB, as planned
In 2016 MMRDA planned to fund the civil works itself and the rest with the Asian Development Bank (Indian Infrastructure). No loan agreement for Line 2B was read.
ReportedIndian Infrastructure (opens source in a new tab)
Daily riders by 2031
10.5lakh a day (projected)
VerifiedMMRDA (opens source in a new tab)
Depot
Mandale31.4 ha
VerifiedMMRDA (opens source in a new tab)
Interchanges
  • Chembur for Mumbai Monorail at V N Purav Marg, and the Harbour line at Chembur
VerifiedMMRDA (opens source in a new tab)
Planned: EEH for Metro Line 4 (Wadala-Kasarvadavali), at Siddharth Colony. ReportedConstruction World (opens source in a new tab)
Planned: Income Tax Office for Metro Line 3 (Aqua Line). Reportedoneindia.com (opens source in a new tab)
Travel time
50 to 75% shorterthan by road today, depending on traffic (MMRDA)
VerifiedMMRDA (opens source in a new tab)

Progress

MMRDA publishes one progress table for Line 2B, updated monthly. It covers the whole line, open stretch included, and does not split it by station or phase.

Phase I, Mandale to Diamond Garden

  1. PlanningDoneLine 2B approved by the State Cabinet, 27 Sep 2016 (reported)
  2. Tenders and designDoneCivil contract CA-07 to NCC, Apr 2019 (reported)
  3. Civil constructionDoneMandale depot complete (MMRDA)
  4. Systems and trainsDoneTrial runs from 16 Apr 2025 (reported)
  5. Testing and safety approvalDoneSafety commissioner's final inspection from Sep 2025 (reported)
  6. OpeningDoneOpen since 7 Apr 2026

Phase IA, Diamond Garden to Chembur

  1. PlanningDoneLine 2B approved by the State Cabinet, 27 Sep 2016 (reported)
  2. Tenders and designDoneBalance works L2B-C102 to NCC, 6 Apr 2023 (reported)
  3. Civil constructionDoneChembur station 100% complete by April 2026 (reported)
  4. Systems and trainsDoneRuns with the Phase I trains
  5. Testing and safety approvalDonePassed before the opening
  6. OpeningDoneOpen since 13 Aug 2026

Chembur to D N Nagar

  1. PlanningDoneLine 2B approved by the State Cabinet, 27 Sep 2016 (reported)
  2. Tenders and designDoneBalance works to J Kumar, 28 May 2021, and to NCC, 6 Apr 2023 (reported)
  3. Civil constructionNowPiers 99%, U and I girders 90%, 31 Aug 2026
  4. Systems and trainsNot startedNo source found
  5. Testing and safety approvalNot startedNo date announced
  6. OpeningNot startedReported target: 2027 for Diamond Garden to Saraswat Nagar

Civil works complete, as of

  • Pile cap100%
  • Pier works99%
  • Pier cap and portal beam99%
  • U and I girder works90%
  • Mandale depot works100%

VerifiedMMRDA (opens source in a new tab)

Tenders and contracts

Every package we could trace, with its value in crore rupees. MMRDA keeps only current notices online, so most of these come from trade press.

PackageScopeFloatedEstimateAwardedAwarded toStatusSource
CA-04BViaduct and stations of the western section, about 12.7 km from D N Nagar towards BKCNot foundNot publishedNot published20 Dec 2017Simplex InfrastructuresCancelledReportedThe Metro Rail Guy (opens source in a new tab)
CA-06Viaduct and 6 stations, MTNL Metro to Chembur, Kurla Terminus includedNot found₹483.05 cr₹521.21 cr3 Mar 2018RCC Infra Ventures and MBZ (JV)CancelledReportedThe Metro Rail Guy (opens source in a new tab)
CA-07Viaduct and 5 stations, Diamond Garden to Mandale depotNot found₹420.08 crNot publishedApr 2019NCCAwardedReportedThe Metro Rail Guy (opens source in a new tab)
CA-14Mandale depot, civil worksNot foundNot publishedNot published2017RCC Infra Ventures and MBZ (JV)CancelledReportedThe Metro Rail Guy (opens source in a new tab)
L2B-C101Balance works of CA-04B: 12.824 km of viaduct and 10 stations, ESIC Nagar to ILFSNot found₹1,167.65 cr₹1,307.88 cr28 May 2021J Kumar InfraprojectsAwardedReportedThe Metro Rail Guy (opens source in a new tab)
L2B-C102Balance works of CA-06: 5.868 km of viaduct and 5 stations, MTNL Metro to ChemburNot found₹635.71 crNot published6 Apr 2023NCCAwardedSources conflictThe Metro Rail Guy (opens source in a new tab)
L2B-C103Balance civil works of the Mandale depot (CA-14)Not found₹464.75 cr₹530.32 crNov 2020Ahluwalia ContractsAwardedReportedThe Metro Rail Guy (opens source in a new tab)
CA-249Electrical and mechanical works, five stations from Diamond Garden to MandaleFeb 2024₹30.04 cr₹33.95 crJul 2024Colossus Infra ProjectsAwardedReportedThe Metro Rail Guy (opens source in a new tab)

Who is building it

Stations

All 20, in order from ESIC Nagar, the first station from D N Nagar, to Mandale, then the one an earlier plan had. Names follow MMRDA. Select a station to ride to it, or open its own page.

  1. 01ESIC Nagarएसिक नगरStation page: ESIC Nagar
  2. 02Prem Nagarप्रेम नगरStation page: Prem Nagar
  3. 03Indira Nagarइंदिरा नगरStation page: Indira Nagar
  4. 04Nanavati Hospitalनानावटी हॉस्पिटलStation page: Nanavati Hospital
  5. 05Khira Nagarखीरा नगरStation page: Khira Nagar
  6. 06Saraswat Nagarसारस्वत नगरStation page: Saraswat Nagar
  7. 07National Collegeनॅशनल कॉलेजStation page: National College
  8. 08Bandra Metroबांद्रा मेट्रोInterchange: Western Railway suburban, BandraStation page: Bandra Metro
  9. 09Income Tax Officeइनकमटॅक्स ऑफिसInterchange: Metro Line 3 (Aqua Line)Station page: Income Tax Office
  10. 10ILFSआय एल एफ एसStation page: ILFS
  11. 11MTNL Metroएम टी एन एल मेट्रोStation page: MTNL Metro
  12. 12SG Barve Margएस जि बर्वे मार्गStation page: SG Barve Marg
  13. 13Kurla (E)कुर्ला (पूर्व)Interchange: Central Railway suburban, KurlaStation page: Kurla (E)
  14. 14EEHइ. इ. एच.Station page: EEH
  15. 15ChemburचेंबूरInterchange: Central Railway Harbour line, Chembur (about 200 m), Mumbai Monorail, V N Purav Marg (about 100 m)OpenStation page: Chembur
  16. 16Diamond Gardenडायमंड गार्डनOpenStation page: Diamond Garden
  17. 17Shivaji Chowkशिवाजी चौकOpenStation page: Shivaji Chowk
  18. 18BSNL Metroबी एस एन एल मेट्रोOpenStation page: BSNL Metro
  19. 19Mankhurdमानखुर्दInterchange: Central Railway Harbour line, MankhurdOpenStation page: Mankhurd
  20. 20Mandale Metroमंडाळे मेट्रोOpenStation page: Mandale Metro

In an earlier plan, not on MMRDA's list now

Station list and order VerifiedMMRDA (opens source in a new tab) station count VerifiedMMRDA (opens source in a new tab)

Updates

The latest reported milestones, each linked to the article or document, posts on X picked by hand, and news that a script finds every six hours.

On X

Posts by MMRDA and Maha Mumbai Metro, whose claims count as verified, and by people who follow the project, whose claims count as reported.

  1. Hrishi @Hrishix_

    A new I-girder is in place at Juhu Circle. He expects this section to be finished in one to one and a half months, and trial runs possible in six to seven months. Two videos.

  2. Swarup Bodke @bodkeitis

    The Shunya bridge over the Vakola nallah in BKC: girders are launched on the Mandale side, but there is no progress over the nallah yet, and the cables are still to be put in. Two photos.

  3. Swarup Bodke @bodkeitis

    The curved cantilever bridge over the Mithi river will join soon: only 5 to 10% of the work is left before both ends meet. Two photos.

  4. Swarup Bodke @bodkeitis

    Kurla (E) station: finishing work under way, roofing in its last stage. Three photos.

  5. Rajendra B. Aklekar @rajtoday

    The girders for Line 2B's crucial curve at the Nehru Nagar signal in Kurla (E) have been assembled. Four photos.

  6. Rajendra B. Aklekar @rajtoday

    Work on the crucial curve on SG Barve Marg at the Nehru Nagar signal, Kurla (E), has gathered pace after a building was demolished. Three photos.

  7. Hrishi @Hrishix_

    Platform screen doors have started arriving on phase 2, D N Nagar to Saraswat Nagar. Track work is complete past Juhu Circle; overhead wire and signalling work is going on; the roof structure is in place. Juhu Circle should be done in three to four months. Two photos.

  8. Swarup Bodke @bodkeitis

    A 64 m girder launched on CST Road, in front of the Kurla depot and Kanakia Zillion. Three photos.

  9. Haldilal @haldilal

    MTNL Metro station in BKC. Video.

  10. Swarup Bodke @bodkeitis

    A photo of Line 2B works, in a thread of metro photos.

  11. Maha Mumbai Metro @MMMOCL_Official

    Chembur station, newly opened, as a multimodal hub for the neighbourhood. Video.

  12. Swarup Bodke @bodkeitis

    The pylon of the cable-stayed bridge over the Western Railway is taking shape on the Kalanagar side; temporary supports are in place to set the girders. Two photos.

  13. MMRDA @MMRDAOfficial

    Three composite steel girders across the Central Railway between Kurla and Vidyavihar, launched within two weeks over running suburban lines, in short railway blocks. Video.

  14. Arindam Mahapatra @Maha7Arindam

    A girder launch for Line 2B near Tilak Nagar station. Quoting his earlier post: work is slow between Kurla (E) and Kurla Metro, where some piers were only recently started, and girders are being cast on site. One photo.

Timeline

From the first report in 2016 to the reported opening target. Dates show only as much precision as the source gives.

  1. MMRDA approves the draft plan: 23.6 km, 22 stations

    MMRDA approves the draft plan for the D N Nagar-Mankhurd corridor, at about Rs 10,970 crore, with ADB funding planned and completion by the end of 2019.

    PlanningReportedIndian Infrastructure (opens source in a new tab)

  2. State Cabinet approves Line 2B

    The Maharashtra Cabinet approves Metro 2B together with Metro 4. The project report puts Line 2B at Rs 10,986 crore.

    ApprovalReportedPressReader (opens source in a new tab)

  3. Foundation stone

    Prime Minister Narendra Modi and Chief Minister Devendra Fadnavis lay the foundation stones of Lines 2B and 4 in Mumbai.

    ConstructionReportedThe Metro Rail Guy (opens source in a new tab)

  4. Western section to Simplex Infrastructures

    Civil package CA-04B, about 12.7 km from D N Nagar towards BKC, goes to Simplex Infrastructures.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  5. Eastern section contracts awarded

    CA-06 (MTNL Metro to Chembur) to RCC Infra Ventures and MBZ (JV), Rs 521.21 crore, and CA-07 (Diamond Garden to Mandale) to Neeraj-Guan (JV), Rs 393.01 crore, the lowest bids.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  6. CA-07, Diamond Garden to Mandale, to NCC

    After several rounds of re-bidding, NCC takes the civil package for the five stations from Diamond Garden to Mandale.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  7. Three contracts ended for poor progress

    MMRDA ends the contracts of Simplex Infrastructures (CA-04B) and of RCC Infra Ventures and MBZ (CA-06 and the Mandale depot, CA-14) for poor progress, and tenders the balance works again.

    ConstructionReportedThe Metro Rail Guy (opens source in a new tab)

  8. First U-girders

    NCC places the first two U-girders, 25 m long, near Deonar depot east of Shivaji Chowk station.

    ConstructionReportedThe Metro Rail Guy (opens source in a new tab)

  9. Mandale depot to Ahluwalia Contracts

    The balance civil works of the Mandale depot (L2B-C103) go to Ahluwalia Contracts for Rs 530.32 crore after negotiation.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  10. D N Nagar to ILFS to J Kumar Infraprojects

    J Kumar Infraprojects receives the balance works of the western section (L2B-C101): 12.824 km and 10 stations, ESIC Nagar to ILFS, for Rs 1,307.88 crore over 30 months.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  11. MTNL Metro to Chembur to NCC

    NCC receives the balance works of CA-06 (L2B-C102): 5.868 km and five stations, MTNL Metro to Chembur, over 36 months. Its bid was Rs 791.15 crore.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  12. Electrical and mechanical works for Phase I

    Colossus Infra Projects wins the electrical and mechanical works of the five stations from Diamond Garden to Mandale (CA-249), Rs 33.95 crore.

    AwardReportedThe Metro Rail Guy (opens source in a new tab)

  13. Trial runs begin, Mandale to Diamond Garden

    MMRDA starts trial runs on the 5.5 km stretch from Diamond Garden to Mandale.

    ConstructionReportedIndian Infrastructure (opens source in a new tab)

  14. Safety commissioner's final inspection begins

    The Commissioner of Metro Rail Safety begins the final inspection of the 5.39 km Mandale-Diamond Garden stretch.

    ConstructionReportedIndian Infrastructure (opens source in a new tab)

  15. Phase I opens, Mandale to Diamond Garden

    Five stations and 5.5 km open: Mandale, Mankhurd, BSNL Metro, Shivaji Chowk and Diamond Garden. Inaugurated on 7 Apr, open to riders from 8 Apr.

    ConstructionVerifiedMMRDA (opens source in a new tab)

  16. Three girders over the Central Railway

    MMRDA launches three composite steel girders across the Central Railway between Kurla and Vidyavihar within two weeks, over running suburban lines, in short railway blocks.

    ConstructionVerified@MMRDAOfficial on X (opens source in a new tab)

  17. Phase IA opens: Chembur

    Chembur station opens, 0.29 km past Diamond Garden, close to the Harbour line and the Monorail.

    ConstructionVerifiedMMRDA (opens source in a new tab)

  18. Reported target: Diamond Garden to Saraswat Nagar

    Free Press Journal (Apr 2026) gives 2027 as the scheduled completion of the next stretch. MMRDA has announced no date.

    Still to comeReportedFree Press Journal (opens source in a new tab)

Sources and corrections

Every figure on this page links to where it came from. This is how to read the marks next to them.

  • Verified Confirmed by MMRDA or its published project report.
  • Reported From a news or trade source, not confirmed by MMRDA.
  • Unverified Could not be confirmed. Treat with care.
  • Sources conflict Sources disagree. Alternatives are shown.

Primary sources

The full list, with every news and trade source, is in SOURCES.md.