Airport Colony
19.10612, 72.85397 (MMRDA's alignment file, Mar 2025)
Choose a station on the map or in the list.
Street level
The street view for the chosen station appears here.
Mumbai Metro, Andheri (E) to the airport. The unofficial tracker.
All linesEdition of Facts checked Not affiliated with MMRDA
Line 7A carries Line 7 on from Andheri (E) to the airport: one elevated station at Airport Colony, then a tunnel to Terminal 2. Both tunnels are bored; on 31 Aug 2026, MMRDA put the airport station's roof slab at 64 per cent. An airport height limit near Airport Colony holds up part of the work. 2 stations in all.
VerifiedMMRDA (opens source in a new tab)
Ride the lineTwo stations, Airport Colony to the airport. Scroll to ride the line. Distances follow MMRDA's alignment file of March 2025, from Airport Colony; the 0.46 km from Gundavali, where 7A leaves Line 7, is not drawn.
Station 1 of 2
0.00 km from the start of the line at Airport Colony VerifiedMMRDA (opens source in a new tab)
Under construction Verified
Station 2 of 2
2.46 km from the start of the line at Airport Colony VerifiedMMRDA (opens source in a new tab)
Change for Metro Line 3 (Colaba-SEEPZ)ReportedThe Metro Rail Guy (opens source in a new tab)
Underground station
Under construction Verified
A hollow line marks track under construction; a dashed line marks the underground stretch. No stretch is open.
The line on a street map. Choose a station to see where it sits, what surrounds it and what the street looks like today. The route and stations come from MMRDA's alignment file of March 2025.
Route, MMRDA's alignment file; under constructionVerifiedMMRDA (opens source in a new tab)
Underground stretch, MMRDA's 2.195 km measured back from the end of the tracks
19.10612, 72.85397 (MMRDA's alignment file, Mar 2025)
Choose a station on the map or in the list.
The street view for the chosen station appears here.
Station data last reviewed 30 Oct 2026.
The line in figures. Old figures stay on the page, struck through, so you can see how the project changed.
MMRDA publishes a detailed progress table for 7A, by part of the line (viaduct, elevated station, ramps, cut and cover, tunnels, airport station). The site shows one or two key items from each part.
Part of the elevated stretch near Airport Colony is above the height the airport allows for the overhead wire; up to about Rs 250 crore of work may have to be rebuilt.
Free Press Journal (27 Aug 2026): the Airport Colony ramp needs 2.4 m more for the overhead wire masts, other places 0.025 m to 2.244 m; more than Rs 260 crore of civil works at risk; MMRDA's Director (Metro Project) said the requirement was not flagged at the design stage by the general consultant, SYSTRA-CEG-SMCIPL. Re-Mumbai: the Airports Authority of India's permits of 2 Jan 2024 (station and ramp) and March 2024 (viaduct) set heights below the design; work stopped in the affected areas. Construction World (8 Oct 2026): the Airports Authority's final technical assessment is pending.
ReportedFree Press Journal (opens source in a new tab)Also: Re-Mumbai, Construction World
Every package we could trace, with its value in crore rupees. MMRDA keeps only current notices online, so most of these come from trade press.
| Package | Scope | Floated | Estimate | Awarded | Awarded to | Status | Source |
|---|---|---|---|---|---|---|---|
| CA-48 | Viaduct, ramp, bored tunnels and both stations of 7A | Not found | Not published | ₹1,998 crSep 2019 | J Kumar Infraprojects | Awarded | ReportedThe Metro Rail Guy (opens source in a new tab) |
| MMRDA notice 12/02/2021-9255 | Diversion of the 1,800 mm sewer line crossing the 7A alignment near the airport | 2 Dec 2021 | Not published | Not found | Not found | Unknown | VerifiedMMRDA (opens source in a new tab) |
| MMRDA notice 09/28/2022-1888 | Consultant to obtain the coastal zone (CRZ) clearance and update the environmental report of Lines 9 and 7A | 28 Sep 2022 | Not published | Not found | Not found | Unknown | VerifiedMMRDA (opens source in a new tab) |
| CA-176 | Power: 33 kV and 25 kV cabling, overhead wire with switching station, auxiliary power, SCADA, for Lines 9 and 7A | Not found | ₹108.01 cr | Not publishedJun 2025 | Leena Powertech-Umesh Brothers JV | Awarded | ReportedThe Metro Rail Guy (opens source in a new tab) |
Both, in order from Airport Colony to the airport. Names follow MMRDA. Select a station to ride to it, or open its own page.
Station list and order VerifiedMMRDA (opens source in a new tab) station count VerifiedMMRDA (opens source in a new tab)
The latest reported milestones, each linked to the article or document, posts on X picked by hand, and news that a script finds every six hours.
No posts picked yet.
Posts appear here only after a person has checked them.
Found automatically in the outlets' own feeds, not checked by a person. Last new item found .
From the first report in 2018 to the reported opening target. Dates show only as much precision as the source gives.
Every figure on this page links to where it came from. This is how to read the marks next to them.
The full list, with every news and trade source, is in SOURCES.md.
Tell us what is wrong and where you saw the right figure. Corrections are public and dated.
Report a correction on GitHub