Station 29 of 32 on Mumbai Metro Line 4, which will run fully elevated from Wadala through Ghatkopar, Mulund and Thane to Kasarvadavali, and on to Gaimukh as Line 4A. Elevated. Part of Phase 1, Gaimukh to Cadbury Junction.
No ground photo yet
Dated photos of Vijay Garden from the street will appear here.
- Where
19.25835, 72.97016 (MMRDA's alignment file, Mar 2025)
- Along the line
Drawn from MMRDA's alignment file of March 2025, turned so Bhakti Park Metro is on the left. 30.4 km from the start of the line at Bhakti Park Metro
- Next stations
- Towards Wadala: Dongari Pada
- Towards Gaimukh: Kasarvadavali
- Interchange
None announced
- Around the station
- On the 4.4 km stretch from Gaimukh to Vijay Garden where the first trial run was held, 22 Sep 2025.ReportedFree Press Journal (opens source in a new tab)
- Construction
Built. Trial runs on the Gaimukh-Cadbury Junction stretch; awaiting the CMRS safety report.
Free Press Journal (22 Aug 2026) names this station among the eight of the first stretch to open.
- When it opens
No date has been announced for this station on its own. For Phase 1, Gaimukh to Cadbury Junction, the target is Dec 2026.