Dongari Pada metro station
डोंगरीपाडा मेट्रो स्थानक
Station 28 of 32 on Mumbai Metro Line 4, which will run fully elevated from Wadala through Ghatkopar, Mulund and Thane to Kasarvadavali, and on to Gaimukh as Line 4A. Elevated. Part of Phase 1, Gaimukh to Cadbury Junction.
No ground photo yet
Dated photos of Dongari Pada from the street will appear here.
- Where
19.25051, 72.97307 (MMRDA's alignment file, Mar 2025)
- Along the line
Drawn from MMRDA's alignment file of March 2025, turned so Bhakti Park Metro is on the left. 29.5 km from the start of the line at Bhakti Park Metro
- Next stations
- Towards Wadala: Tikuji-Ni-Wadi
- Towards Gaimukh: Vijay Garden
- Interchange
None announced
VerifiedMMRDA (opens source in a new tab)
Planned: Thane Integral Ring Metro (Maha-Metro).
The ring metro's official route map has a Dongripada station 186 m from Line 4's Dongari Pada (its map file, read 19 Oct 2026). Neither project calls the two an interchange. The ring line's Manpada is about 560 m from Line 4's Tikuji-Ni-Wadi, not at Line 4's Manpada.
ReportedThane Ring Metro (official) (opens source in a new tab)
- Construction
Built. Trial runs on the Gaimukh-Cadbury Junction stretch; awaiting the CMRS safety report.
Free Press Journal (22 Aug 2026) names this station among the eight of the first stretch to open.
- When it opens
No date has been announced for this station on its own. For Phase 1, Gaimukh to Cadbury Junction, the target is Dec 2026.
- Name
Dongari Pada
Dongari Pada on MMRDA's English page; Dongripada in its alignment file and its Marathi page (डोंगरीपाडा).
VerifiedMMRDA (opens source in a new tab)
In Marathi: डोंगरीपाडा
Facts checked . All 32 stationsThe full Line 4 tracker