Gowniwada metro station
Station 31 of 32 on Mumbai Metro Line 4, which will run fully elevated from Wadala through Ghatkopar, Mulund and Thane to Kasarvadavali, and on to Gaimukh as Line 4A. Elevated. Part of Phase 1, Gaimukh to Cadbury Junction.
No ground photo yet
Dated photos of Gowniwada from the street will appear here.
- Where
19.27669, 72.95803 (MMRDA's alignment file, Mar 2025)
- Along the line
Drawn from MMRDA's alignment file of March 2025, turned so Bhakti Park Metro is on the left. 32.9 km from the start of the line at Bhakti Park Metro
- Next stations
- Towards Wadala: Kasarvadavali
- Towards Gaimukh: Gaimukh
- Interchange
None announced
- Around the station
- On the 4.4 km stretch from Gaimukh to Vijay Garden where the first trial run was held, 22 Sep 2025.ReportedFree Press Journal (opens source in a new tab)
- Construction
Built. On the first stretch, Gaimukh to Cadbury Junction; awaiting the CMRS safety report.
Free Press Journal (22 Sep 2025) counts 10 stations on the first stretch, which takes in this one; its report of 22 Aug 2026 names 8 and leaves this station out. No source says why.
Sources conflictFree Press Journal (opens source in a new tab)
- When it opens
No date has been announced for this station on its own. For Phase 1, Gaimukh to Cadbury Junction, the target is Dec 2026.
- Name
Gowniwada
Gowniwada in the Line 4A project report (Oct 2017); 'Gownipada' in MMRDA's alignment file (Mar 2025); 'Govaniwada' in news reports. MMRDA's Line 4 page does not list Line 4A's stations. No Marathi name found in an MMRDA source.
Sources conflictMMRDA DPR, Line 4A (2017) (opens source in a new tab)
Marathi name not yet found in a source.
Facts checked . All 32 stationsThe full Line 4 tracker