Station 32 of 32 on Mumbai Metro Line 4, which will run fully elevated from Wadala through Ghatkopar, Mulund and Thane to Kasarvadavali, and on to Gaimukh as Line 4A. Elevated. Part of Phase 1, Gaimukh to Cadbury Junction.
No ground photo yet
Dated photos of Gaimukh from the street will appear here.
- Where
19.28436, 72.94695 (MMRDA's alignment file, Mar 2025)
- Along the line
Drawn from MMRDA's alignment file of March 2025, turned so Bhakti Park Metro is on the left. 34.4 km from the start of the line at Bhakti Park Metro
- Next stations
- Towards Wadala: Gowniwada
- Gaimukh is the last station.
- Interchange
None announced
VerifiedMMRDA (opens source in a new tab)
Planned: Metro Line 10 (Gaimukh-Shivaji Chowk, Mira Road), approved.
Line 10 is approved, not built. Its first station is listed as Gaimukh Reti Bunder.
- Around the station
- On the 4.4 km stretch from Gaimukh to Vijay Garden where the first trial run was held, 22 Sep 2025.ReportedFree Press Journal (opens source in a new tab)
- Construction
Built. Trial runs on the Gaimukh-Cadbury Junction stretch; awaiting the CMRS safety report.
Free Press Journal (22 Aug 2026) names this station among the eight of the first stretch to open.
- When it opens
No date has been announced for this station on its own. For Phase 1, Gaimukh to Cadbury Junction, the target is Dec 2026.
- Name
Gaimukh
Line 4A's last station and, until the Mogharpada depot is ready, the line's pit line for stabling and maintenance (Free Press Journal, 22 Aug 2026). No Marathi name found in an MMRDA source. MMRDA's alignment file puts it about 360 m further along than the 2017 report's chainage, against under 100 m at every other station: the Line 4A route or the station moved after 2017 (no source says which).
VerifiedMMRDA DPR, Line 4A (2017) (opens source in a new tab)
Marathi name not yet found in a source.
Facts checked . All 32 stationsThe full Line 4 tracker