Station 32 of 32 on Mumbai Metro Line 4, which will run fully elevated from Wadala through Ghatkopar, Mulund and Thane to Kasarvadavali, and on to Gaimukh as Line 4A. Elevated. Part of Phase 1, Gaimukh to Cadbury Junction.

No ground photo yet

Dated photos of Gaimukh from the street will appear here.

Where

19.28436, 72.94695 (MMRDA's alignment file, Mar 2025)

See it on the mapOpenStreetMap (opens in a new tab)

VerifiedMMRDA (opens source in a new tab)

Along the line
Drawn from MMRDA's alignment file of March 2025, turned so Bhakti Park Metro is on the left.

34.4 km from the start of the line at Bhakti Park Metro

Next stations
  • Towards Wadala: Gowniwada
  • Gaimukh is the last station.
Interchange

None announced

VerifiedMMRDA (opens source in a new tab)

Planned: Metro Line 10 (Gaimukh-Shivaji Chowk, Mira Road), approved.

Line 10 is approved, not built. Its first station is listed as Gaimukh Reti Bunder.

ReportedThe Metro Rail Guy (opens source in a new tab)

Around the station
Construction

Built. Trial runs on the Gaimukh-Cadbury Junction stretch; awaiting the CMRS safety report.

Free Press Journal (22 Aug 2026) names this station among the eight of the first stretch to open.

ReportedFree Press Journal (opens source in a new tab)

When it opens

No date has been announced for this station on its own. For Phase 1, Gaimukh to Cadbury Junction, the target is Dec 2026.

ReportedFree Press Journal (opens source in a new tab)

Line 4 status and opening date, answered

Name

Gaimukh

Line 4A's last station and, until the Mogharpada depot is ready, the line's pit line for stabling and maintenance (Free Press Journal, 22 Aug 2026). No Marathi name found in an MMRDA source. MMRDA's alignment file puts it about 360 m further along than the 2017 report's chainage, against under 100 m at every other station: the Line 4A route or the station moved after 2017 (no source says which).

VerifiedMMRDA DPR, Line 4A (2017) (opens source in a new tab)

Marathi name not yet found in a source.

VerifiedMMRDA (opens source in a new tab)