Laxmi Nagar metro station
लक्ष्मीनगर मेट्रो स्थानक
Station 7 of 32 on Mumbai Metro Line 4, which will run fully elevated from Wadala through Ghatkopar, Mulund and Thane to Kasarvadavali, and on to Gaimukh as Line 4A. Elevated. Part of Phase 3, Gandhi Nagar to Wadala.
No ground photo yet
Dated photos of Laxmi Nagar from the street will appear here.
- Where
19.09021, 72.91827 (MMRDA's alignment file, Mar 2025)
- Along the line
Drawn from MMRDA's alignment file of March 2025, turned so Bhakti Park Metro is on the left. 8.7 km from the start of the line at Bhakti Park Metro
- Next stations
- Towards Wadala: Pant Nagar
- Towards Gaimukh: Shreyas Cinema
- Interchange
None announced
- Around the station
- The last station on Line 4 to get its land. MMRDA acquired the 16,762 sq m plot in Vikhroli East from Godrej & Boyce in April 2026, after six years of talks (begun 2019) and a 2021 notice withdrawn after a Bombay High Court stay. Every other station on the line is built.ReportedThe Indian Express (opens source in a new tab)
- Construction
Under construction
MMRDA publishes progress for the whole line only (pier work 95%, U-girders 94%, deck slab 92% as of 31 Aug 2026), not by station.
- When it opens
No date has been announced for this station on its own. For Targets reported in September 2025; the first has passed, the reported target is October 2026 to Gandhi Nagar, October 2027 to Wadala.
- Name
Laxmi Nagar
VerifiedMMRDA (opens source in a new tab)
In Marathi: लक्ष्मीनगर
Facts checked . All 32 stationsThe full Line 4 tracker