Manpada metro station
मानपाडा मेट्रो स्थानक
Station 9 of 19 on Mumbai Metro Line 12, which will run fully elevated from Kalyan to Taloja. Elevated. Under construction.

- Where
19.18054, 73.09140 (MMRDA's approved alignment, 20 Mar 2025)
See it on the mapOpenStreetMap (opens in a new tab)The drone flight past it, from 9:30
The 2019 project report (DPR) put it 61 m from here.
- Along the line
Drawn from MMRDA's approved alignment of 20 Mar 2025, turned so Kalyan is on the left. 8.5 km from the start of the line at Kalyan (2019 project report: chainage 7,689.746 m)
- Interchange
None announced
- Around the station
- In the 2019 project report: in Sonar-Pada village, after the alignment leaves Kalyan-Shilphata Road (about ch. 7,182 m) for the proposed DP road of the MMRDA growth centreVerifiedMMRDA DPR (2019) (opens source in a new tab)
- Construction
Under construction (civil works across the corridor)
MMRDA publishes corridor-wide progress only, not per-station progress.
- When it opens
No date has been announced for this station on its own. For Line 12 as a whole, the reported target is May 2028; an earlier reported target was 31 Dec 2027.
Sources conflictFree Press Journal (opens source in a new tab)
- Name
Manpada
Wikipedia lists it as 'Manpada (Dombivali East)'.
ReportedThe Metro Rail Guy (opens source in a new tab)
In Marathi: मानपाडा
Facts checked . All 19 stationsThe full Line 12 tracker